Alerts

FERC Proposes Fast-Start Pricing Reforms in Three Markets

December 28, 2017

In four orders issued December 21, 2017, the Federal Energy Regulatory Commission (FERC) continued its examination of price formation in the wholesale electricity markets administered by Regional Transmission Organizations (RTOs) and Independent System Operators (ISOs).  FERC announced that it was withdrawing a 2016 Notice of Proposed Rulemaking (NOPR) on fast-start pricing, which would have implemented uniform pricing rules across all RTO/ISO markets.  In response to industry concerns about the need to accommodate regional differences, FERC instead initiated three separate proceedings under section 206 of the Federal Power Act (FPA) regarding the pricing of fast-start resources in  the New York ISO (NYISO), PJM Interconnection (PJM), and Southwest Power Pool (SPP) markets, alleging that specific elements of these markets’ approaches to fast-start resources require reform.  FERC initiated paper hearings on whether the identified aspects of each market’s fast-start resource rules are unjust and unreasonable, and thus must be reformed.

Background: FERC’s Initial Price Formation Inquiries and the Fast-Start Resource NOPR

In 2014, FERC opened a proceeding to examine price formation in organized markets.  The proceeding aimed to ensure that pricing rules established in RTO/ISO markets would satisfy four objectives:

“(1) maximize market surplus for consumers and suppliers; (2) provide correct incentives for market participants to follow commitment and dispatch instructions, make efficient investments in facilities and equipment, and maintain reliability; (3) provide transparency so that market participants understand how prices reflect the actual marginal cost of serving load and the operational constraints of reliably operating the system; and (4) ensure that all suppliers have an opportunity to recover their costs.”

Following a series of workshops with market participants, FERC staff released a December 2014 report on “Operator-Initiated Commitments” in RTO/ISO markets.  The report expressed concern that fast-start resources may be ineligible to set prices, particularly when the resource is off-line prior to being dispatched, and then immediately dispatched to the maximum operating level (and therefore unavailable to serve the next increment of load).  The report also indicated that even in circumstances where fast-start resources are eligible to set prices, some RTO/ISO markets may not allow such prices to reflect the resource’s start-up and no-load commitment costs. 

In an effort to address these concerns, FERC issued a NOPR on fast-start pricing in December 2016 (Docket No. RM17-3).  The NOPR defined “fast-start resource” as “any resource that is able to start up within ten minutes or less, that has a minimum run time of one hour or less, and that submitted an economic energy offer to the market.”  FERC proposed to require that each RTO/ISO incorporate five pricing elements:

  1. Application of fast-start pricing to any resource that meets the above definition;

  2. When a RTO/ISO commits a fast-start resource, it should incorporate the unit’s commitment (start-up and no-load) costs in energy prices;

  3. RTOs/ISOs must modify pricing to relax the economic minimum operating limit of fast-start resources to treat them as fully dispatchable between zero and the maximum operating limit;

  4. For offline fast-start resources to set prices to address certain system needs, the resource must be feasible and economic; and

  5. RTOs/ISOs must incorporate fast-start pricing into both day-ahead and real-time markets.

FERC’s December 21, 2017 Orders Terminate Rulemaking and Instead Propose Market-Specific Pricing Reforms in PJM, NYISO, and SPP

In response to industry concerns over the need to consider regional variations in resource mix and other factors, FERC terminated the Docket No. RM17-3 rulemaking and initiated paper hearings concerning the fast-start pricing rules utilized in the PJM, NYISO, and SPP markets. 

PJM (Docket No. EL18-34): FERC proposes six reforms to PJM’s treatment of fast-start resources, and proposed to require PJM to include definitions for “fast-start resource” and “block-loaded resource” in PJM’s tariff:

  1. PJM currently does not allow the economic minimum operating limit of block-loaded resources to be relaxed by more than 10 percent; FERC finds that this could restrict the set of circumstances in which these units could set prices, and that PJM should allow relaxation of the economic minimum operating limit of these resources by up to 100%.

  2. PJM currently limits fast-start pricing to block-loaded resources; the order would require that any unit capable of providing the necessary market service should be able to set prices, including more flexible fast-start resources that nevertheless have minimum operating levels.

  3. PJM  dispatches units based on minimum operating limits, but without respecting power balance constraints, which may result in dispatch costs that are not least-cost and may stress frequency regulation resources; FERC indicates that “fast-start pricing logic would ideally not change the dispatch of resources away from the cost-minimizing dispatch but would only alter the manner by which prices are established.”

  4. FERC proposes to allow unit commitment costs to be reflected in price.

  5. PJM’s tariff does not limit the minimum run-time requirement for fast-start resources; FERC proposes to allow fast-start resources to set prices only where their minimum run time is one hour or less, on the theory that units with longer run times are not truly marginal.

  6. PJM allows resources with start-up times of up to two hours to be eligible fast-start resources; FERC indicates that allowing units with start-up times of greater than one hour to set price may be unjust and unreasonable.

NYISO (Docket No. EL18-33): FERC proposes two reforms to the NYISO’s tariff:

  1. FERC proposes to require NYISO to modify pricing logic to allow fast-start resources’ start-up costs to be reflected in prices (FERC indicates no-load costs are already included). 

  2. Similar to the proposed reforms in the PJM market, FERC proposes to require the relaxation of all dispatchable fast-start resources’ economic minimum operating limits by up to 100 percent for the purpose of setting prices, and not just those resources that are block-loaded. 

SPP (Docket No. EL18-35): FERC proposes five reforms to SPP’s treatment of fast-start resources (termed “quick-start resources” in the SPP tariff):

  1. SPP’s commitment process “screens” fast-start resources that would be dispatched below their minimum operating limit, which FERC believes may lead to dispatch schedules based on a list of resources not actually reflective of available resources and may ignore resources’ physical limitations.

  2. As with NYISO and PJM, FERC indicates that SPP does not include fast-start resources’ commitment costs in pricing, and indicates that start-up and no-load costs should be included.

  3. As with PJM, SPP does not have a minimum run-time requirement for fast-start resources; FERC proposes to limit eligibility for fast-start treatment to resources with minimum run times of one hour or less.

  4. SPP currently does not allow for the relaxation of the economic minimum operating limits for block-loaded or other fast-start resources for price-setting purposes; FERC proposes that these limits should be relaxed to allow for incorporation in market pricing.

  5. Unregistered fast-start resources (that may meet the physical requirements of the category, but are not registered as such) do not have fast-start pricing rules applied to them at present.  FERC indicates that this may be unjust and unreasonable, and suggests that pricing based on physical attributes (regardless of registration status) may be more appropriate.

In the orders issued for all three regions, the Commission addressed concerns raised in response to the Fast-Start Pricing NOPR about “price-chasing” that may result from fast-start pricing – i.e., where units dispatched down to make room for fast-start resources may have an incentive to “chase” higher LMPs by not following the dispatch instruction, which could in turn lead to over-generation imbalances.  The Commission proposed that PJM, NYISO, and SPP consider approaches to discouraging this behavior “such as penalizing uninstructed deviations, settling over-generated MWh at only standard LMP (not at the higher prices determined through fast-start pricing), or providing for lost opportunity cost payments.”

Next Steps

In all three proceedings, FERC is using paper hearing procedures, which allow submittal of briefs directly to the Commission.  Interventions will be due January 18, 2018.  Initial briefs will be due February 12, 2018, and reply briefs will be due March 13, 2018.  Briefs may be submitted by the three market operators and any other intervenors, and may include data or empirical analysis to support retention of their current tariff structures or alternative tariff structures.  FERC anticipates issuing orders in each proceeding by September 2018. 

Analysis

The withdrawal of the Fast-Start Pricing NOPR and the commencement of paper hearing orders concerning the pricing logic used in the PJM, NYISO, and SPP regions reflects FERC’s recognition that a one-size-fits-all approach to price formation may not be appropriate given differing resource portfolios and levels of renewable resource penetration in different regions.  Nevertheless, the pricing reforms proposed by FERC in each region indicate FERC’s clear preference that (i) fast-start resources should be able to set price through 100% relaxation of minimum operating level constraints; (ii) such relaxation for pricing purposes should not impact economic dispatch; (iii) the price set by a fast-start resource should reflect the resource’s no-load and start-up costs; and (iv) fast-start pricing should be limited to resources with start and minimum run times of one hour or less.  FERC recognizes that implementing such reforms could create an incentive to chase prices – a frequent criticism of relaxing operating constraints in price formation – and has proposed a handful of tools the regions might use to combat this behavior. 

Notably, these pricing reforms proposed by FERC would apply only to fast-start resources capable of starting within one hour and running for one hour or less. The types of coal and nuclear resources which are the subject of the Secretary of Energy’s proposed rule pending before the Commission in Docket No. RM18-1 typically would not fall within the definition of fast-start resources.  Such resources could, however, benefit from higher locational marginal prices driven by these proposed pricing reforms.

###

Van Ness Feldman represents clients on a full range of issues arising out of the organized markets regulated by FERC.  If you are interested in additional information regarding FERC’s recent orders and their implications, please contact  Doug SmithJustin MoellerGabe Tabak,  or any member of the firm’s Electric Practice at (202) 298-1800 in Washington, D.C. or in Seattle at (206) 623-9372.

Follow us on Twitter @VanNessFeldman

Alert Authors

Douglas W. Smith
Washington, DC
Email »

Related Professionals

Related Services & Industries

Electric